Propeller

Propeller

Propeller

Tittle

Showing posts with label Ministry of Works. Show all posts
Showing posts with label Ministry of Works. Show all posts

Tuesday 10 July 2018

THIRD MAINLAND BRIDGE TO BE CLOSED FOR REPAIRS


The Federal Controller of Works in Lagos, Mr Adedamola Kuti, said on Tuesday that consultations had begun for the closure of the Third Mainland Bridge for repairs.



Kuti said that the ministry of works was going to hold a meeting with stakeholders tomorrow to discuss how to manage traffic during the repairs.

He, however, did not specify the exact date the bridge would be closed to traffic or how long the repairs would last.

According to him, stakeholders attending the meeting to discuss the repairs include traffic regulatory agencies, transport unions, truck owners and drivers’ unions, law enforcement agents, among others.

“The Federal Executive Council has approved the maintenance work on the Third Mainland Bridge in Lagos State.

“The project has taken off already and in carrying out the work, we may at certain times be shutting down the bridge for maintenance.

“At the moment we may begin with tests on the bridge, so, we may shut it by 12 midnight on Thursday and carry out tests and some repairs and open it to traffic by midnight on Sunday.’’

He said that six other damaged bridges across the state were already undergoing maintenance and rehabilitation.

“We have contracts on maintenance of some of the bridges in Lagos.

“We are completing maintenance work on the expansion joints on the Coconut Bridge.

“We are expecting the contractor to start work on the Independence Bridge in Lagos.

“There is repair work going on currently on the Apapa Bridge, that is, Ijora/Leventis Bridge.

“Maintenance work is ongoing on the Ijora-7up Bridge, we are also changing the expansion joints.

“On the bridge around the National Stadium area, we are putting covers to all the stolen manholes, we are replacing the steel covers from stadium to Costain,” he said.

The controller said that some tests had been carried out on the Otedola Bridge, whose surface was recently burnt during a tanker fire.

Kuti said that the tests revealed that the bridge was safe for use and that the contractors would soon attend to the bridge.

AgegePulse Magazine

Saturday 23 September 2017

LASG Set To Proffer Lasting Solution To Incessant Flooding on Akilo Road, Agege


Lagos State Government has embarked on clearing of silts and reconstruction of drainages at Akilo Road, Agege to tackle incessant flooding ravaging the area.



Over the years, residents and commuters along popular Akilo Road, Agege are often thrown into distress due to constant flooding whenever it rains.

Moreover, there has been several efforts on the part of the community to address the cause of the flooding but the unruly dumping of wastes into gutter from different parts of Ogba Ijaye and Agege has continued to block drainages on Akilo Road.



However, the state government in its efforts to ensure a flood free state swiftly responded to complaints of the residents as Lagos State Public Works Corporation have began the clearing of silts and reconstruction of drainages on the road.

The exercise which began last week is still in progress due to the length of Akilo road.

When Agegepulse visited the site, one of the LSPWC supervisors, Mr. Taiwo Akintokun explained that apart from clearing the silt, the agency will also dig the drainages deeper and wider adding that the drainages will be channelled to a bigger drainage on ACME Road for easy flow of water.